Final stage this autumn 2022
In 2018, it was decided to renovate our house (built in 1985) in a 3-year plan.
In a first phase in spring 2019, the two restaurant halls as well as the lobby, bar and reception area were modernised.
In autumn 2019, the first room renovation (4th floor – 14 rooms & suites) was scheduled. At the same time, the large wellness, spa & pool area was also 100% newly planned and designed.
After a Covid-related changeover break, we took a break in the Finally, 14 rooms on the 3rd floor were renovated in autumn 2021. At the same time, the entire heating system in the hotel was replaced and a new one installed.
We thus offer guests 50% of all rooms at top standard and 100% renovated.
Follow our transformation and work on Insta or Facebook.